• Home
  • >
  • Project Detail
  • Project Snapshot

    Name of Project: 220 kV and 132 kV Grid Substation and associated transmission lines and associated scheme/works under RAJ/PPP-8

    Circuit Length – 115 Ckms

    Transformation Capacity – 310 MVA

    Concession / TSA Term: 115 Ckms

    Circuit Length – 35 Years

    Regulator – Rajasthan Electricity Regulatory Commission

    Project Rating – A- (CARE)

    Beneficiary State / Off-taker – Rajasthan

    Business Model – Build Own Operate Maintain

    Project Mode – Intra State

    Project Highlights

    • Before time completion of the Project
    • Proven historical operating performance – achieved availability higher than target availability
    • Strong O&M team with maintenance plan ensuring periodic maintenance
    • Counter party risk protection through Payment Pooling Mechanism
    • Counter party risk linked to CTU (PGCIL)
    • Fixed tariff – all tariff through non escalable component
  • About the Project

    Hadoti Power Transmission Ltd was incorporated on May 10, 2013.HTSL was awarded to ATL (Adani Transmission Ltd.) by Rajasthan Rajya Vidyut Prasaran Nigam Ltd. on Mar 31, 2017 for 25 year period on BOOM basis. HPTSL entered into a Transmission Service Agreement with Long Term Transmission Customer on Aug 11, 2017.

    The transmission system established under HPTSL meets the power demand in the Rajasthan state. HPTSL operates five EHV overhead transmission lines with total circuit length of approximately 115 Ckms and five nos. Grid substation of 310 MVA capacity in the state of Rajasthan. The project construction started in November 2017 and completed in Feb 2019 and project was fully commissioned in Feb 2019.

    Numerous challenges were encountered and dealt with while completing the project. Three key challenges encountered and successfully dealt with were –

    • Severe Right of Way issue :

    There was severe resistance faced during construction of project in the region of Kota, Peeplu. This was overcome with close coordination with stakeholders and proactive support from administration.

    • Hard Rock Soil Starta and Hilly substation Location :

    Hard Rock soil strata was encountered during the construction of line in Kota area. This was overcome using innovative techniques and construction methodology. The substation location at Chitri and Bambora were at hilly location.

    • Scattered Locations :

    Since, all the elements were scattered in Rajasthan state, arranging for logistic was a challenging task. Close coordination with all suppliers and using centralized storage and semi storage at Substation helped ensure effective supply chain management.

  • Project Details
    Transmission line/Substation Route Length (Ckms) Specification Scheduled COD Actual COD
    LILO 220kV S/C Kota-Badod & Kota- Modak Line at Ranpur, LILO of 132 kV S/C Kota - Mandana Town line, LILO of 132 kV S/C Mahaveer Nagar Deoli Manjhi line & 220kV GSS Ranpur, Kota Dist. 30 220 kV D/C (Hexa)

    132 kV D/C (Panther)
    Feb-2019 20-Feb-2019
    132kV S/C Malpura –Peeplu Line & 132kV GSS Peeplu, Tonk Dist. 40 132 kV S/C (Panther) 13-Jan-2019
    LILO of 132 kV S/C Seemalwara - Sagwara line & 132kV GSS Chitri, Dungarpur Dist. 4 132 kV D/C (Panther) 30-Apr-2018
    132 kV GSS Salumbar S/C line associated with 132 kV GSS Bambora & )132kV GSS Bambora, Udaipur Dist. 25 132 kV S/C (Panther) 06-Jan-2019
    LILO of 132 kV S/C Nadbai – Weir line associated with 132 kV GSS Khatoti & )132kV GSS Khatoti, Bharatpur Dist. 16 132 kV D/C (Panther) 05-May-2018
  • Project Availability
  • Image Gallery
© 2018 Adani Group
Disclaimer
cancel

Adani Transmission Limited retains copyright on all the text, contents, graphics and trademarks displayed on this site. All the text, graphics and trademarks displayed on this site are owned by Adani Transmission Limited.

The information on this site has been included in good faith and is for general purpose only and should not be relied upon for any specific purpose. The user shall not distribute text or graphics to others without the express written consent of Adani Transmission Limited. The user shall also not, without Adani Transmission Limited’s prior permission, copy and distribute this information on any other server, or modify or reuse text or graphics on this or any another system.

Although Adani Transmission Limited tries to ensure that all information and recommendations, whether in relation to the products, services, offerings or otherwise (hereinafter "information"), provided as part of this website is correct at the time of inclusion on the web site, Adani Transmission Limited does not guarantee the accuracy of the Information. Also, not all of the information may be up to date in all respect. Adani Transmission Limited makes no representations or warranties as to the completeness or accuracy of Information. Certain links in this site connect to other Web Sites maintained by third parties over whom Adani Transmission Limited has no control. Adani Transmission Limited makes no representations as to the accuracy or any other aspect of information contained in such other Web Sites.

Adani Transmission Limited hereby disclaims all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for any particular purpose, title and non-infringement. In no event will Adani Transmission Limited, its related partnerships or corporations, or the partners, agents or employees thereof be liable for any decision made by the user and/or site visitor for any inference or action taken in reliance on the information provided in this site or for any consequential, special or similar damages. Applicable Law and Jurisdiction of this Disclaimer are governed by and to be interpreted in accordance with laws of India, without regard to the choice or conflicts of law provisions of any jurisdiction. The user/site visitor agrees that in the event of any dispute arising in relation to this Disclaimer or any dispute arising in relation to the web site whether in contract or tort or otherwise, to submit to the jurisdiction of the courts located at Ahmedabad (Gujarat) (India) only for the resolution of all such disputes.

Except for the historical information herein, statement in this website, which includes words or phrases such as “will”, “aim”, “will likely result”, “would”, “believe”, “may”, “expect”, “will continue”, “anticipate”, “estimate”, “intend”, “plan”, “contemplate”, “seek to “, “future”, “objective”, “goal”, “likely”, “project”, “should”, “potential”, “will pursue”, and similar expressions or variations of such expressions may constitute “forward-looking statements”. These forward-looking statements involve a number of risks, uncertainties and other factors that could cause actual results to differ materially from those suggested by the forward-looking statements. These risks and uncertainties include, but are not limited to our liability to successfully implement our strategy, our growth and expansion plans, obtain regulatory approvals, our provisioning policies, technological changes, investment and business income, cash flow projections, our exposure to the market risks as well as other risks. The company does not undertake any obligation to update forward-looking statements to reflect events or circumstances after the date thereof.